管道组成件组对时使用内径对口器

管道组成件组对时使用内径对口器
2021年01月05日08:22:22 0 418

内径校准器用于装配管道部件

4.11管道组装和预装配

4.12管段组装时,垫层应设置牢固,定位可靠,防止焊接变形。

4.13管段找正时应检查管段的平直度,允许偏差为1mm/m,但全长最大累计偏差不得超过10mm。

4.14组装管道组件时,应使用内径校准器。

4.14.1管段组装时,不得采用强对中或加热管子的方法,以消除接口端面间隙过大、错位和不同心。当发现这些缺陷时,应检查相邻或相关管段的尺寸,然后对缺陷零件进行纠正和返工。

4.15管道上仪表的源件应先钻孔,再按规定位置焊接。不得取出源孔的倒角部分。

4.16管道预装配前,应对管道部件进行检查和清洗,符合下列条件后方可进行组装:

4.16.1管道构件的材质、规格、型号应符合设计要求;

4.16.2管道构件内外表面的泥土、油污等杂物已清理干净

4.16.3完整标识。

4.17管道预组装时,应检查整体尺寸、各零件尺寸及调整余量,其偏差应符合下列要求:

4.17.1总长度L在各方向上的允许偏差为±5mm;

4.17.2间距n,允许偏差±1.5mm;

4.17.3支管与主管的横向偏差C为±1.5mm;

4.17.4靠近法兰面的螺栓孔应安装在跨中,F的允许偏差为±LMM;

4.17.5法兰端面应垂直,E的允许偏差为:

a、 公称直径小于或等于300mm时;

b、 公称直径大于300mm时,不得大于2mm。

4.18同壁厚管道组装时,内壁应齐平,错边不得超过下列要求

10%壁厚,沙级管道不大于0.5mm;

SHB、SHC管内壁差1.0mm或外壁差2mm;

4.19管道预制应便于运输和安装,组装应具有足够的刚度和强度,否则应采取临时加固措施,必要时应标明吊装索具的绑扎点。

4.20管段预制完成后,应编号保护。


The inner diameter aligner is used in the assembly of pipe components

4.11 pipe assembly and pre assembly

4.12 when the pipe section is assembled, the cushion shall be set firmly and positioned reliably to prevent deformation during welding.

4.13 the straightness of the pipe section shall be checked when the pipe section is aligned, and the allowable deviation is 1 mm / m, but the maximum cumulative deviation of the whole length shall not exceed 10 mm.

4.14 when assembling pipe components, inner diameter aligner shall be used.

4.14.1 during the pipe section assembly, it is not allowed to use the method of strong alignment or heating the pipe to eliminate the excessive clearance, misalignment and non concentricity of the interface end face. When these defects are found, the size of adjacent or related pipe sections shall be checked, and then the defective parts shall be corrected and reworked.

4.15 the source parts of instruments on the pipeline shall be drilled first and then welded according to the specified position. The chamfered part of the source hole shall not be taken out.

4.16 before pipeline pre assembly, the pipeline components shall be inspected and cleaned, and can be assembled only when the following conditions are met:

4.16.1 the material, specification and model of pipe components shall meet the design requirements;

4.16.2 the soil, oil dirt and other sundries on the internal and external surfaces of pipe components have been cleaned up

4.16.3 complete identification.

4.17 during pipeline pre assembly, check the overall size, each part size and adjustment allowance, and their deviation shall meet the following requirements:

4.17.1 the allowable deviation of the total length L in each direction is ± 5mm;

4.17.2 spacing n, the allowable deviation is ± 1.5mm;

4.17.3 the lateral deviation C between branch pipe and main pipe is ± 1.5mm;

4.17.4 the bolt holes adjacent to the flange surface should be installed in the middle of the span, and the allowable deviation of F is ± LMM;

4.17.5 the flange end face shall be vertical, and the allowable deviation of E is:

a. When the nominal diameter is less than or equal to 300 mm;

b. When the nominal diameter is greater than 300 mm, it shall not be greater than 2 mm.

4.18 when the pipes with the same wall thickness are assembled, the inner wall shall be flush, and the misalignment shall not exceed the following requirements

10% of the wall thickness and no more than 0.5mm for Sha grade pipeline;

The inner wall difference of SHB and SHC pipes is 1.0 mm or the outer wall difference is 2 mm;

4.19 pipeline prefabrication shall be convenient for transportation and installation, and the assembly shall have sufficient rigidity and strength, otherwise temporary reinforcement measures shall be taken, and the binding point of hoisting rigging shall be marked when necessary.

4.20 after the prefabrication of pipe section, it is necessary to number and protect it.


管道组成件组对时使用内径对口器

 

4.11管道组对、预组装

4.12管段组对时,座垫置牢固,定位可靠,防止在焊接过程中产生变形。

4.13管段对口时应检查组对的平直度,允许偏差为1㎜/m,但全长的最大累计偏差不得超过10mm。

4.14管道组成件组对时,使用内径对口器。

4.14.1、管段组对时,不得采用强力对口或加热管子的方法来消除接口端面的过量间隙、错边与不同心等缺陷。当发现这些缺陷时,应检查相邻或相关管段的尺寸,然后对产生缺陷的部位应进行校正和返工。

4.15管道上仪表取源部件应按规定位置先钻孔后焊接。温度计取源部件的开孔,不得向里倒角。

4.16管道预组装前,应对管道组成件进行检查与清理,具备下列条件方可组装:

4.16.1、管道组成件的材质、规格、型号应符合设计要求;

4.16.2、管道组成件内外表面的泥土、油垢及其他杂物等已清理干净:

4.16.3、标识齐全。

4.17管道预组装时,应检查总体尺寸与各部尺寸及调节裕量,它们的偏差应符合下列要求:

4.17.1每个方向总长L允许偏差为±5㎜;

4.17.2间距N,允许偏差为±1.5㎜;

4.17.3支管与主管的横向偏差c,允许值为±1.5mm;

4.17.4法兰面相邻的螺栓孔应跨中安装,f的允许偏差为±lmm;

4.17.5法兰端面应垂直,e的允许偏差为:

a.公称直径小子或等于300mm时不大于lmm;

b.公称直径大于300mm时不大于2mm。

4.18壁厚相同的管道组对时,内壁平齐,其错边量不超过下列规定

SHA级管道为壁厚的10%,且不大于0.5mm; 

SHB、SHC级管道内壁差1.0mm或外壁差2mm;

4.19管道预制应方便运输和安装,组合件应有足够的刚度与强度,否则应有临时加固措施,必要时应标出吊装索具捆绑点的位置。

4.20管段预制完成后,应做好编号及防护保管工作。

点赞(0) 打赏
weinxin
管业咨询
规格、型号、日报价、厂家源头货源。
历史上的今天
07月
05
合肥mpp电缆护套管,mpp电缆护套管,合肥,mpp,电缆,护套 管件管材

合肥mpp电缆护套管

合肥mpp电缆护套管合肥mpp电缆护套管产品说明合肥mpp电缆护套管一家专业从事管道生产制造的高科技企业,拥有先进的塑胶管材生产设备,拥有高素质的职工队伍。产品广泛应用于各地的电信...
建材,百科全书,金属,重量,计算,公式 管件管材

建材百科全书丨金属重量计算公式

常用的一些金属材料重量计算公式,钢管重量计算公式,方钢重量计算公式,钢板重量计算公式。• 园钢重量(公斤)=0.00617×直径×直径×长度• 方钢重量(公斤)=0.00785×边...
波纹管 管件管材

波纹管是啥

波纹钢管(板)优点1、波形钢板涵同时具有刚性和柔性:结构受力合理,荷载分布均匀,具有一定的抗变形能力。2、采用标准化设计,工厂规模化生产:生产周期短,效率高,有利于降低成本,提高质...
mpp电力管,电力管的优势,mpp,电力,对比,传统,管的,优势 管件管材

mpp电力管对比传统电力管的优势

mpp电力管对比传统电力管的优势MPP电力管采用改性聚丙烯为主要原材料,是无须大量挖泥、挖土及破坏路面,在道路、铁路、建筑物、河床下等特殊地段敷设管道、电缆等施工工程。与传 统的“...
pv,电力,安装,指南 管件管材

PVC电力管安装指南

PVC电力管安装指南(一)CPVC电力管管铺管安装1、CPVC电力套管标准定长(6米)管材配置管枕3付,管枕间距为2.0m,管枕距接头处为0.5 m。2、CPVC电力护套管下管可由...
pv,通讯,用双壁,波纹管 管件管材

PVC-U通讯用双壁波纹管

PVC-U通讯用双壁波纹管产品描述:    PVC-U双壁波纹管是以硬聚氯乙烯为主要原料,PVC双壁波纹管分别由内、外挤出,一次成型,内壁平滑,外壁呈梯形波纹状...

评论列表 共有 0 条评论

暂无评论